Project Scope
ABM Mechanical provided plumbing and HVAC for a KC-135 Hanger, along with all of its supporting spaces. The hanger floor is 28,000 sq. ft., which also includes an in-floor radiant heating system. The heating plant has three, four million BTU, natural gas fired Fulton boilers. The building also has a central compressed air system, and an air craft wash system. There are Trane air handlers located on the Mezzanines, which are located in the hanger bay to provide conditioned air throughout the building. There is an exterior ground mounted chiller which provides cooling for the office spaces. Automatic compressed hose reels were installed in the hanger bay by ABM.
Project Team
ABM’s Role: Plumbing & HVAC
Owner: Maine Air National Guard
General Contractor: Sheridan Corp.
Subcontractors: Damon Insulation, Hahnel Bros., Hughes Engineering, Air Solutions
Special Project Considerations
Helped design and install door track drains, and provided heat under the doors to keep them from freezing during cold temperature weather.